In this matter, groundWork and the South Durban Community Environmental Alliance (SDCEA) are challenging an environmental authorisation granted to Phinda Power Producer (Pty) Ltd (Phinda Power) by the Acting Chief Director of Integrated Environmental Authorisations (the Chief Director). The environmental authorisation was granted in respect of Phinda Power’s proposed 320MW Emergency Risk Mitigation gas to power plant, to be built in the Richard’s Bay Industrial Development Zone.

 This review application comes as a result of the Minister’s dismissal of groundWork’s appeal.

  1. Notice of Motion (19 May 2022)
  2. Founding Affidavit of Avena Jacklin and Annexures (18 May 2022)
  3. Rule 16A Notice (18 May 2022)
  4. Rule 41A Notice (18 May 2022)